This project was a multi-floor electrical infrastructure project which was completed in various phases. WBE installed a new electrical riser system through the California Tower, Montgomery Tower, and the Sacramento Tower and each floor in each tower received a new distribution board that was used to provide power to all the building’s loads. The project also included replacement of transformers and panelboards throughout the building.

WBE worked with the building’s Fire/Life-Safety vendor, PAFA, to upgrade the FLS system to meet the new design as required. WBE also provided infrastructure and electrical connections as required for plumbing and mechanical trades. This project took nearly two years to complete and most of the work was done at night.